Beware of that Old Abandoned Building: A Guide to Remodeling
By: Michael G. E. Mount, AIA
Issue: February/March 2006
Untitled Document
Most cities and towns have experienced periods of time where buildings in their
communities, for whatever reason, have become abandoned, later to be either remodeled
for a different use or demolished to make room for something new. There appears
to be a general opinion among many public building planners and decision makers
that there will invariably be some inherent construction cost savings in the
remodeling of an existing building, simply because it is existing. Depending
on a number of variables that will be explored below, this may be true in some
cases, maybe even in most cases. But time and again it has been proven that in
some specific instances it can be more expensive to remodel an existing building
than to construct a new building for the same use.
Remodeling an Existing Building
Remodeling an existing building is generally economical if the building is
in relatively good condition and the proposed use for the building requires
relatively simple, straight-forward building systems. However, if the proposed
use for the existing building is for a forensic laboratory, it must be understood
that the building systems to be included in this remodel project are of a
highly technical, specialized, and complex nature. This will necessitate
a thorough examination of the existing building in order to assess its suitability
to be remodeled into a crime lab.
In some cases it might be financially prohibitive to remodel an existing building
regardless of the complexity of its intended use. The fact that the building
has at least a foundation, exterior walls, and a roof might not be enough to
render it a feasible candidate for remodeling. An initial assessment of an
existing building should include determining the age of the building and obtaining
construction drawings and specifications of the building, if they are available.
Here are some of the items that should be examined and assessed.
Condition of Existing Utilities. Existing utilities include mechanical, plumbing,
electrical, and telecommunications equipment and their respective distribution
systems. The condition and capacity of existing boilers, chillers, air handlers,
duct work, plumbing fixtures, piping, transformers, generators, power panels,
and wiring are a few of the items that should be examined to determine if they
have any remaining useable life or if they should be replaced, and what costs
might be involved.
Building Code Compliance. Most regulating agencies require that the design
for the remodel of an existing building shall include all necessary upgrades
required to render the building in complete compliance with current building
codes. Since building codes are constantly being revised to include more stringent
requirements, this could result in some significant additional construction
costs, depending on the age of the building and the extent of the upgrades
required for building code compliance. The assessment of any building being
considered for a remodel should include a complete building code analysis.
Asbestos. The U.S. Environmental Protection Agency has identified forty-six
building materials that may contain asbestos (www.epa.gov/Region6/6pd/ asbestos/asbmatl.htm).
Although the use of asbestos containing materials is currently illegal in most
jurisdictions, they were used without restrictions in building construction
as recently as the 1980s. If asbestos is determined to be present, most building
authorities would require the total abatement of the asbestos which, depending
on the age of the building and the extent of the asbestos materials, can be
another very costly effort.
Structural Condition. Directly related to building code compliance is an assessment
of the structure of the building. This issue can be particularly critical in
earthquake and hurricane zones, where local building codes are frequently upgraded
to include more stringent requirements for the structural resistance to these
natural forces.
Infestations. Is the building considered old? Does it have a history of water
infiltration, either through roof leaks or at window and door openings? Is
the basic structure wood? If the answer to any of these questions is yes, the
building should be examined for mold and termites. Mitigation of these types
of infestations can be costly.
Roof Condition. Although the structural integrity of the roof may be sound,
it is critical to assess the weather-tight integrity of the finished roofing
system and materials, including its age, repair history, and its replacement
cost. Any needed, expensive roofing replacement or repair costs should be addressed
as part of the project’s development costs.
Interstitial Space. The space within a building between the ceiling and the
structure for the floor or roof above is called the interstitial space. An
adequate amount of interstitial space is essential for the successful, efficient,
and economical design of a forensic laboratory, yet this is probably the most
overlooked item when assessing an existing building. The interstitial space
for a forensic laboratory will include distribution systems for HVAC ductwork,
fire sprinkler lines, domestic and treated laboratory water lines, power and
data lines, light fixtures, plumbing drains, and waste lines. It will include
exhaust ductwork for fume hoods, instrumentation equipment, drying rooms, cyanoacrylate
cabinets, bullet recovery tanks, and firing range supply and exhaust. Figure
1 (on page 20) shows the interstitial space in the corridor of the Sacramento
County Forensic Laboratory. In this particular design a ceiling was not provided
in the corridor in order to provide ready access for maintenance, but also
to show the myriad of utility distribution systems located in the building’s
interstitial space. An optimum vertical dimension for the interstitial space
in a crime lab is 4 feet. Assuming a floor-to-ceiling height of 9 feet and
3 feet for the floor or roof structure above, an ideal floor-to-floor (or floor-to-roof)
dimension is 16 feet.
Feasibility Evaluation
Evaluating the financial feasibility of remodeling an existing building into
a forensic laboratory involves applying two simple cost formulas. Application
of these cost formulas is the simple part, but determining the value of the
applicable variables in each formula will involve a careful and thorough
building evaluation and construction cost exercise. Variables for the formulas
are:
N = Construction cost for building a totally new forensic laboratory in lieu
of remodeling an existing building. This is the control variable.
D = Cost of demolition, removal, and disposal of items in the existing building
that have no more useful life. This variable also includes asbestos abatement.
S = Current value of all systems and materials that have useful life and
can remain as part of the existing building, i.e., the cost associated with
these items if they were to be constructed new.
A = New construction cost for all systems and materials that must be added
to the building, which theoretically should equal N - S.
T = Total construction cost for remodeling the existing building into a forensic
laboratory.
The two simple formulas are:
T = N - S + D
T = D + A
In order for the remodel project to be financially feasible, T must be less
than N.
The estimated cost for construction of a new forensic laboratory building,
variable “N,” can be determined by evaluating historical construction
cost data from recently constructed crime labs. According to the data maintained
by SmithGroup, on a national average a crime laboratory can be constructed
for approximately $280 per square foot. This figure will vary depending on
the size of the laboratory, geographical location, and other variables that
can be assessed by an architect who is familiar with forensic laboratory design.
Variables “D,” “S,” and “A” can be determined
through line-item cost estimating using cost estimating guides and formats
such as those provided by the Construction Specifications Institute (CSI) or
R.S. Means Company. Again, an architect with experience in the design of forensic
laboratories can determine these costs figures as part of the existing building
assessment.
Let us examine two possible scenarios where an existing building is being
considered as a remodel project for a new crime lab.
Scenario 1
Let us assume that a comprehensive needs assessment has determined that the
new crime lab needs 41,500 square feet of floor space. An abandoned, fifteen
year old, 40,000 square foot warehouse is being considered, and it is determined
that design efficiencies can be incorporated to absorb the 1,500 square foot
deficit. A thorough building analysis has revealed that the building’s
structure meets current building codes, it contains no asbestos, and its
entire roof was replaced less than five years ago. Ninety percent of the
floor area is open warehouse space with a clear inside height to the bottom
of the roof structure of 14 feet. The remaining ten percent of the building
consists of office spaces. The minimal amount of demolition required is limited
to some interior partitions and doors and some saw-cuts in the floor slab
for laboratory drains. As a warehouse facility the mechanical, plumbing,
and electrical infrastructure are minimal, but it is determined that the
existing HVAC systems can be used to partially satisfy the HVAC needs for
the crime lab’s administrative office spaces.
After conducting a thorough cost analysis, the following was revealed:
(1) Demolition will amount to $175,000 (variable “D”).
(2) The existing building systems and components that have useful life include
the foundation, floor slab, exterior walls and insulation, roof structure and
roofing, HVAC system, and minimal amounts of plumbing and electrical infrastructure.
The value of these systems and components, i.e., what it would cost to construct
them today, is determined to be approximately $2,150,000 (variable “S”).
(3) The building and laboratory systems and components that will have to be
added into this building are extensive. Some of the more significant items
are interior partitions, doors, ceilings and finishes; laboratory casework,
fume hoods, and equipment; upgraded mechanical, plumbing, electrical, and telecommunications
infrastructure and distribution systems. The estimated cost for these items
is approximately $9,050,000 (variable “A”).
(4) At $280 per square foot, a new 40,000 square foot building, finished
and equipped as a forensic laboratory, will cost $11,200,000 (control variable “N”).
Now let us apply the formula, T = N - S + D, where N = new construction,
S = value of useful existing systems and components, and D = demolition
costs.
T = $11,200,000 - $2,150,000 + $175,000
T = $9,225,000 = estimated remodel construction cost.
Testing the above results with the second formula, T = D + A, where D = demolition
cost and A = cost of new systems and materials to be added.
T = $175,000 + $9,050,000
T = $9,225,000 = estimated remodel construction cost. “T” being
less that “N” shows a savings in construction cost in this scenario
of $1,975,000 less than the cost for new construction.
Figure
1: Sacramento County Crime Laboratory main corridor showing the extensive
utility systems located in the interstitial space.
Scenario 2
This scenario has a totally different set of parameters. We will assume that
the 41,500 square feet space need for the crime lab as described in Scenario
1 still applies. The existing building being considered is a two-story office
building, twenty-five years old, with 22,000 square feet per floor, slightly
larger than needed, but close enough that the excess space will be put to
good use. The structure of the building is pre-cast concrete, and despite
its age it is structurally sound and complies with current building codes.
Clear vertical space from the floor to the structure above on both floors
is 10 feet. A new roof was installed less than five years ago.
It appears that demolition costs will be extensive. Most of the interior of
the building will have to be gutted. The existing office partitions and doors
are showing the effects of age and are not in a floor plan configuration that
is conducive to an efficient forensic laboratory layout. Interior finishes,
including carpet, tile, and ceilings are worn and must be removed. The building
does contain asbestos in pipe insulation and flooring material. There is also
evidence of mold in some of the partitions, the extent of which will not be
determined until demolition occurs. The HVAC systems include the original equipment
and ductwork, which has been repaired extensively over the years, all of which
has outlived its useful life.
On the positive side, the building has a good foundation and building enclosure,
including floors, walls and roof structure, and a weather-tight roof. It also
has an elevator that is in good operating condition.
The cost analysis for this building reveals the following information:
(1) Demolition will include the removal all interior partitions, doors, ceilings
and finishes; abatement of asbestos and mold; removal of all mechanical and
plumbing equipment and their respective distribution systems; and saw cutting
in the floor slab for laboratory drains. Estimated cost for demolition is
$2,250,000 (variable “D”).
(2) The existing building systems and components that have useful life include
the foundation, floor slab, second floor structure, exterior walls and insulation,
roof structure and roofing, and minimal amounts of the electrical infrastructure.
The value of these systems and components is determined to be approximately
$2,050,000 (variable “S”).
(3) Like Scenario 1, the building and laboratory systems and components that
will have to be added into this building are extensive. Some of the more significant
items are interior partitions, doors, ceilings and finishes; laboratory casework,
fume hoods, and equipment; new mechanical, plumbing, electrical, and telecommunications
infrastructure and distribution systems. The estimated cost for these items
is approximately $10,270,000 (variable “A”).
(4) At $280 per square foot, a new 44,000 square foot building, finished and
equipped as a forensic laboratory, will cost $12,320,000 (control variable “N”).
(5) An additional construction cost increase that is not applicable to the
building in Scenario 1 will have to be added to the cost for this building.
This cost premium is the result of the low floor-to-structure height of 10
feet. Although the minimum standard ceiling height for a forensic laboratory
space is 9 feet, it can go as low as 8.5 feet, which is the recommended minimum
for adequate installation and connections of fume hood exhaust ducts. This
would result in an interstitial space of less than 1.5 feet, and would necessitate
some very awkward and undesirable designs for utility distributions. An example
would be the need to provide soffits above wall casework in order to run ductwork
and other utilities horizontally below the ceiling height. Lengthy utility
runs might be needed where inadequate interstitial space will not allow utilities
to cross over each other. Installation of some utilities between structural
members or through the web components of beams and joists might be required.
These and other undesirable design features resulting from inadequate interstitial
space will increase, not only the construction costs, but also the architectural
and engineering design fees. We will call this new variable “P” and
the additional premium cost that might be expected in this building is $650,000.
Now let us apply the new formula, T = N - S + D + P, where N = new construction,
S = value of useful systems and components, D = demolition costs, and P = the
premium paid for inadequate interstitial space.
T = $12,320,000 - $2,050,000 + $2,250,000 + $650,000
T = $13,170,000 = estimated remodel construction cost.
Testing the above results with the second formula and adding the P variable,
T = D + A + P, where D = demolition cost,
A = cost of systems and materials to be added, and P = the premium paid for
inadequate interstitial space.
T = $2,250,000 + $10,270,000 + $650,000
T = $13,170,000 = estimated remodel construction cost. “T” being
greater than “N” shows that the construction cost for remodeling
the building in this scenario would cost $850,000 more than new construction.
One additional check that can be made is to compare variables “D” and “S.” If
D is greater than S, the remodel project will not be financially feasible.
If “D” is less than “S” the project will be feasible.
This is a shortcut check that should not preclude a thorough examination of
all cost variables in order to be assured of the feasibility of the project.
Conclusion
The above two scenarios both represent potential reality. In searching for
an existing building to be remodeled into a forensic laboratory, some, most,
or even all of the conditions described above might be encountered.
Michael Mount has devoted the past 20 years of his career as an architect
almost exclusively to the planning and design of forensic laboratories. He
is currently a principal with SmithGroup. The combined experience within SmithGroup's
nine offices includes the planning and design of over 6-million square feet
of forensic facilities throughout the United States and abroad. Michael can